NERC specifies transmission systems planning standards that
cover the types of contingencies that must be examined for conditions for all
facilities in service and with facilities out-of-service for maintenance while
delivering generator output to projected customer demands and providing
contracted firm (non-recallable reserved) transmission services, at all demand
levels.
These contingencies can result in the loss of single or
multiple components. For each of the contingencies, the system must be stable
and applicable thermal and voltage limits must be observed.
For the loss of multiple components, the controlled
interruption of customer demand, the planned removal of generators, or the
curtailment of firm (non-recallable reserved) power transfers may be
necessary.10
The standards also require evaluation of the risks and
consequences of a number of extreme contingencies such as the loss of all
circuits on a R-O-W, all generators at a generating station, or failure of
circuit breakers to clear a fault. Individual Regions may develop their own
regional planning criteria to reflect circumstances applicable to their own
situation.
These Regional Criteria are evaluated by NERC to ensure
consistency with NERC’s planning standard.
NERC also covers in its Planning Standards:
• Reliability assessment;
• Facility connection requirements;
• Voltage support and reactive power;
• Transfer capability;
• Disturbance monitoring.
The present complexity of the NERC Standards reflects the
changing state of the electric utility industry. When NERC and the Regional
Councils were first formed, their membership was almost entirely utilities and
the rules, standards, best practices that were produced relied on voluntary
observance by the members.
As the industry has moved to its present structure with many
more participants, NERC has been working to make the planning and operating
rules for the utility industry clear, universal, and well documented. To do
this has meant that the volume of the associated material has grown to a point
that no one text could hope to cover it all.
As the footnotes indicate, individuals wishing more detail
on these matters can find them at NERC’s Web site: www.nerc.com.
As a generation expansion pattern was being developed,
transmission planners would address the transmission expansion needed to
accommodate the generation and the forecast load growth. Development of a
transmission plan has been described as part science and part art.There are
three situations that confront the transmission planner:
1. Connect a new generator or generating station to the
grid.
2. Connect a new substation to the grid.
3. Reinforce the existing grid.
The obvious first step for connecting a new generator or a
new distribution substation is to build one or more lines to the nearest bulk
power substation. However, this may not be sufficient or adequate.An
examination is needed to see if the capability of the existing grid is
sufficient to accommodate either.
This examination has to consider a wide range of operating
conditions including different load levels, different power transfer patterns
on the grid, and various maintenance outages. The analysis should evaluate a
number of years into the future including additional generation and
distribution substation requirements.
It may well be that because of future developments, larger
more robust facilities should be installed initially or, even, that future
expansion may mitigate the need for facilities now. For example, if generation
is presently being sited outside a generation deficient load area, an initial
reaction might
be to build a large-scale transmission development into that
area.
What if, however, subsequent generation additions are within
the generation deficient area? The result could be that the transmission
additions could be lightly loaded and do not carry enough power to pay for
their costs.
An important consideration is that the transmission
additions may not always be near the new generation. The restriction on the
capacity of a section of the grid can be far removed from the new generator
addition.
No comments:
Post a Comment